Burnup Chart

Calculate Burnup Chart instantly with the exact formula and a worked example.

Burnup Chart

Current total scopeSP
CompletedSP
Sprints elapsed
Scope growth per sprintSP
Completed of scope
37.5%
Calculate Burnup Chart instantly with the exact formula and a worked example.
Velocity
15.00SP/sprint
Sprints remaining
6.82
Total sprints (forecast)
9.82
Scope at completion
147.3SP

More about: Burnup Chart

What it calculates

The “Burnup Chart” calculator computes Completed of scope in % from 4 parameters: current total scope (SP), done (SP), sprints elapsed, scope growth per sprint (SP).

A handy everyday calculator for daily tasks.

Example calculation

With parameters Current total scope = 120 SP, Done = 45 SP, Sprints elapsed = 3, Scope growth per sprint = 4 SP the result is 37.5 %.

How to use

  1. Enter current total scope, done, sprints elapsed and scope growth per sprint — each field above is adjustable with a slider.
  2. Completed of scope (%) is calculated automatically as you type.
  3. Check the worked example below to see the formula applied to real numbers.
  4. Copy the result or bookmark this calculator.

Related calculators

FAQ

How is Burnup Chart calculated?
The Burnup Chart calculator computes Completed of scope (in %) from current total scope, done, sprints elapsed, scope growth per sprint. Enter your values above and the exact formula is applied instantly; a worked example with real numbers is shown below.
Is the Burnup Chart calculator free?
Yes. It is completely free, needs no signup, runs entirely in your browser, and sends no data to any server.

More calculators in this category

Explore related free tools

Climbing (force)Caving (rope length)Kayaking (river class)Rowing (stroke rate)Sailing (handicap)RC aircraft (thrust)RC models (LiPo)Drone flight timeDrone link rangeAquarium (CO₂ rate)Aquarium (biomass)Aquarium (filter)